Following green light for the deployment of ESA’s Mars Express radar, given in February this year, the radar booms are now planned to be deployed in the first half of May.

 

lefthttp://hypography.com/gallery/files/9/9/8/marsis_water400_thumb.jpg[/img]Once the deployment is successful, the Mars Express MARSIS radar will enable the first European spacecraft to orbit Mars to complement its study of the planet’s atmosphere and surface.

 

MARSIS (Mars Advanced Radar for Subsurface and Ionosphere Sounding instrument) is the first antenna of its kind which was also designed to actually look below the surface of Mars at the different layers of material, most notably for water.

 

The deployment of the three MARSIS radar booms is an operation which will take place in three phases, in a window spanning from 2 to 12 May 2005. These operations will be initiated and monitored from ESA’s European Space Operations Centre (ESOC) in Darmstadt, Germany.

 

Each boom will be deployed separately, with the two 20-metre ‘dipole’ booms to be unfurled first and the 7-metre ‘monopole’ boom to follow a few days later.

 

righthttp://hypography.com/gallery/files/9/9/8/Marsis_antenna_L_thumb.jpg[/img]Before each deployment, the spacecraft will be placed in a ‘robust’ attitude control mode, which will allow it to tumble freely while the boom extends before regaining standard pointing to the Sun and Earth.

 

After each deployment, the control team will conduct a full assessment of the spacecraft status before a decision is taken to proceed with the next phase.

 

The result of each deployment can be assessed only after a series of tests, each taking few days. After the deployment of the three booms, ESA engineers will start the analysis of the complete behaviour of the satellite to be able to confirm the overall success of the operation.

 

The current schedule is subject to changes, because the timing of the complex series of operations cannot be all fixed beforehand. A status report will follow in due course.

 

Once the deployment is complete, MARSIS will undergo three weeks of commissioning before the start of actual science investigations, ready for when one of the prime regions of interest for radar observations comes into the right position through the natural evolution of the spacecraft’s orbit.

 

The MARSIS instrument was developed by the University of Rome 'La Sapienza', Italy, in partnership with NASA’s Jet Propulsion Laboratory (JPL) in Pasadena, California, USA.

 

Source: ESA

Link to comment
Share on other sites

9 May 2005 - The deployment of the second antenna boom of the Mars Express Sub-Surface Sounding Radar Altimeter (MARSIS) science experiment has been delayed pending investigation of an anomaly found during deployment of the first antenna boom.

 

The anomaly was discovered on 7 May towards the end of the first deployment operations. Deployment of the first boom started on Wednesday 4 May. The problem with the boom was confirmed by flight control engineers working at ESA's European Space Operations Centre (ESOC) in Darmstadt, Germany, on 7 May, after which further activity was stopped pending a full assessment of the situation.

 

The decision to delay deployment of Boom 2 pending clarification of the situation and implications was made on 8 May....

 

More

 

Let's hope all goes well.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
×
×
  • Create New...